Pacific Railway

The project aims to connect the Port of Buenaventura with the Central Railway Corridor to optimise freight transport.

Summary


Objective

Revitalize and modernize the Pacific Corridor by connecting Buenaventura with the Central Railway Corridor through a competitive rail system that reduces logistics times and costs.

Key Goals

  • Complete ongoing prefeasibility studies.
  • Initiate and complete feasibility studies estimated at COP 40,000 million.
  • Structure the project under a PPP scheme.
  • Identify potential private investors with experience in railway projects.

Market Opportunity

Reliance on the road transport system has limited competitiveness in the Pacific region. Rail reactivation offers advantages in integration with the Port of Buenaventura, logistics cost reduction, and strengthened export competitiveness.

ESG Considerations

Environmental: Lower carbon footprint compared to road transport; contribution to transport decarbonization.

Social: Job creation and strengthening of logistics and production chains.

Governance: Compliance with CONPES, DNP, and MHCP frameworks; coordination with regional authorities and the private sector.

Financial Indicators


TIR

N/A (prefeasibility stage).

Reference Budget

18 Trillion COP

Contracted Prefeasibility

COP 24,997 Million

Estimated Feasibility

COP 40,000 Million

NPV

N/A (prefeasibility stage).

Project Schedule


Preliminary studies in progress

Duration: Contract signed on December 23, 2022.

Feasibility

Duration: Planned as the next stage, with a COP 40,000 million budget.

Comprehensive Structuring

Duration: PPP scheme following feasibility. (Exact dates not specified in the project sheet.)

Business Model


Key Partners

  • National Infrastructure Agency (ANI)
  • National Government, private investors
  • Technical and financial consultants

Key Activities

  • Prefeasibility and feasibility studies.
  • PPP structuring.
  • Environmental and legal management.

Value Proposition

  • Strategic railway connection between Buenaventura and the Central Corridor
  • Reduced logistics costs and enhanced export competitiveness

Customer Segments

  • Exporters
  • Logistics operators
  • Public sector sponsors
  • Local communities

Revenue Streams

  • PPP model (freight and potential passenger concessions)

Cost Structure

  • Studies
  • Feasibility
  • Design
  • Engineering
  • Licensing
  • Construction
  • Operation
  • Maintenance

Risk Plan


Event Probability Impact Rating
Technical complexity of the route Medium High Significant
Financial risks (PPP, investment attraction) Medium High Significant
Social risks and community acceptance Low High Under Monitoring
Environmental risks (licensing, mitigation) Medium High Significant
Legal processes over existing corridor Medium Medium Under Monitoring

 

$18 billions COP

STATE: In search of investment
Download Brochure

Request Advice

Enter security code:
 Security code

Similar Projects (Seeking Investment)

Texto alterno

International Airport - Meta

Mobility and transport > Aerospace Transport

CAPEX USD 108 million (GBP 86 million) - OPEX USD 132 million (GBP 105 million)

Location

Total investment: ~COP 928 billion (CAPEX USD 108 million / OPEX USD 132 million). Terminal 16,000 m², runway 3.2 km.

CAPEX USD 108 million (GBP 86 million) - OPEX USD 132 million (GBP 105 million)

View project International Airport - Meta
Icon of a train carriage

Bogotá – Central Railway Corridor

Mobility and transport > Rail Transport

$22 billions COP

Location

Connect the Bogotá–Cundinamarca Metropolitan Region with the Central Railway Corridor through a modern, intermodal railway system that reduces logistics times and costs, strengthening national competitiveness.

$22 billions COP

View project Bogotá – Central Railway Corridor
Icon of a person in a boat on the river

Navigability of the Meta River

Mobility and transport > River and Maritime Transport

Given the current progress of the consultancy on the feasibility of the Meta River Navigability project, financial projections and budget figures are not yet available

Location

The aim is to establish a public-private partnership project to reactivate river transport on the Meta River, including the design, construction, operation and maintenance of the necessary infrastructure.

Given the current progress of the consultancy on the feasibility of the Meta River Navigability project, financial projections and budget figures are not yet available

View project Navigability of the Meta River
Icono de un avión con un chulito

Aircraft Inspection - Valle del Cauca

Mobility and transport > Aerospace Transport

$ Between USD 10 to 90 million depending on number of hangars

Location

Establish a world-class aircraft maintenance, repair and overhaul (MRO) facility at Alfonso Bonilla Aragón Airport to provide services to airlines in Latin America, the United States, Mexico and Europe.

$ Between USD 10 to 90 million depending on number of hangars

View project Aircraft Inspection - Valle del Cauca
Icon of an airport runway with an airplane taking off

El Dorado Airport – Maximum development EDMAX

Mobility and transport > Aerospace Transport

COP 12,690 billion

Location

Consolidate El Dorado as a leading hub in Latin America.

COP 12,690 billion

View project El Dorado Airport – Maximum development EDMAX
Texto alterno

Rafael Núñez Airport

Mobility and transport > Aerospace Transport

1.102 billions COP

Location

New 17,360 m² terminal, refurbishment of the existing terminal and car park for 330 vehicles.

1.102 billions COP

View project Rafael Núñez Airport

Request Advice

Enter security code:
 Security code
In search of investment $18 billions COP